| Stages |
Installments to be Paid |
| At the time of Booking / Allotment |
10% of BSP |
| Within 45 days of Booking / Agreement |
10% of BSP |
| On completion of Foundation or 90 days whichever is later |
10% of BSP + 50% EDC & IDC |
| On Completion of 2nd Floor Slab or 125 days whichever is later |
10% of BSP + 50% of PLC + 50%of Parking |
| On Completion of 5th Floor Slab or 160 days whichever is later |
5% of BSP + 50% of EDC & IDC |
| On completion of 8th floor slab or 195 days whichever is later |
5% of BSP + 50% of PLC + 50%of Parking |
On Completion of 11th Floor Slab or 230 days
whichever is later |
5% of BSP |
| On completion of 14th floor slab or 265 days whichever is later |
5% of BSP |
| On completion of 17th floor slab or 300 days whichever is later |
5% of BSP |
| On completion of 20th floor slab or 335 days whichever is later |
5% of BSP |
| On completion of 23th floor slab or 365 days whichever is later |
5% of BSP |
| On completion of Brick work/410 days whichever is later |
5% of BSP |
| On start of internal plaster/455 days whichever is later |
5% of BSP |
| On start of flooring/500 days whichever is later |
5% of BSP |
| On start of External plaster/545 days whichever is later |
5% of BSP |
| On Possession |
5% of BSP + IFMS + Power backup + Club Membership +Registration charges+ other charges as applicable |